06/07/13: Today I accompanied the team (RubyLynn,
community facilitator; Alan Miller, construction lead; Olive Oliveros, pre-k
school teacher) to various hardware stores to price construction materials for
the sewing center project. Alan Miller and
Ta-Reuben (Upper Javier leader) adjusted the project goals, modified the list of materials, and are now on
track to have materials delivered 6/8 (Sat) morning. We will be praying that the seasonal rains
hold off for the next week! Lumber,
concrete mix (bags) & sand, metal roofing, rebar, tie wire, etc., will be
dropped at the “overlooking” place.
Refer to the photos and it will become very obvious. The materials will be walked into the
community by many volunteers as no vehicle or trailer can maneuver the narrow
foot paths. [We sure could use a helicopter!] Construction work will start Monday.