Saturday, June 8, 2013

06/07/13:  Today I accompanied the team (RubyLynn, community facilitator; Alan Miller, construction lead; Olive Oliveros, pre-k school teacher) to various hardware stores to price construction materials for the sewing center project.  Alan Miller and Ta-Reuben (Upper Javier leader) adjusted the project goals,  modified the list of materials, and are now on track to have materials delivered 6/8 (Sat) morning.  We will be praying that the seasonal rains hold off for the next week!   Lumber, concrete mix (bags) & sand, metal roofing, rebar, tie wire, etc., will be dropped at the “overlooking” place.   Refer to the photos and it will become very obvious.  The materials will be walked into the community by many volunteers as no vehicle or trailer can maneuver the narrow foot paths.   [We sure could use a helicopter!]  Construction work will start Monday.
  